Reply To: MPI of martensitic stainless steel

  • Positive Material Identification (PMI)

    caleb-charles

    Member
    28/11/2021 at 4:43 pm

    If the specification requires MPI as the primary inspection method that is what you should apply unless an approval plan is obtained from the customer. That being said is standard practice to remove all residual inspection materials after testing, therefore no contamination shall be present upon completion.

    I would be more concerned that 13%Cr material may oxidize after being exposed to water if FPI process is applied. That type of contamination can damage surface finis and be difficult to remove from threads.

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.